Search Result

1 - 3 (3)
  • 1
Version:  Allplan 2021 / Allplan 2020 / Allplan 2019 / Allplan 2018 / Allplan 2017 / Allplan 2016  | Last modified: 17.06.2021 11:09
2 user(s) found this FAQ helpful

Question:

How can I import data from an earlier version?



Answer:

You can import data from the last three Allplan versions.
Consequently, the following import operations are possible:

Target version <- import possible from version

2017 <- 2014
2016 <- 2013
2015 <- 2012
2014 <- 2011
2013 <- 2009
2012 <- 2008
2011 <- 2006
2009 <- 2005
2008 <- 2004
2006 <- 2003
2005 <- 17
2004 <- 16

We cannot guarantee that data created in older versions can be imported and edited. The conversion of older data may be incomplete, which may affect intelligent components in particular.


1. Archived data from an earlier version (not older than three previous versions):

There are two ways to convert the data to the current version:

  • Import the project backups created and archived using the
    Services application -> Data Backup -> Import -> Projects.
    After importing the projects, convert them by opening each project once.
  • Import the backups archived using the
    Services application -> File -> Restore documents of any version to '...\Extern'.
    The data are written to the external path.
    You can now process the converted data in ProjectPilot.



2. Archived data from an older Allplan version (older than three previous versions):

  • See whether you can use the approach described in step 1 to import the old projects.
  • If available, it is a good idea to install an old Allplan version. Import the backups created and archived into this old version and convert the projects using the Services application. If you have imported a complete project backup, convert the data by opening each project once. When finished, repeat this process with a newer version (up to three versions later) until the data are up-to-date.
  • If an old Allplan version is not available, you can also have the data converted by Allplan. Please note that this service is not free of charge. Please contact Technical Support -> support.de@allplan.com.




Notes:

  • You can convert the data of all projects at once. Read the following FAQ in Allplan Connect: https://connect.allplan.com/en/faqid/20090408124904.html
  • If enough hard disk space is available, you are advised to keep and maintain the projects so that Allplan automatically converts them to the current version whenever you upgrade.
  • If there are project-specific smart symbol catalogs, you should open the smart symbol catalog once to convert the data.
Download PDF  FAQ_EN_Transferring_data_from_old_Allplan_versions_....
Version:  Allplan 2020 / Allplan 2019 / Allplan 2018 / Allplan 2017 / Allplan 2016 / Allplan 2015 / Allplan 2014 / Allplan 2013 / Allplan 2012  | Last modified: 14.07.2021
1 user(s) found this FAQ helpful

Task:

You have installed Allplan on several local workstations. Now you want to change the installation so that you can access a common network drive.



Note:

Before you switch to a network installation, it is essential that you back up all the data of all the workstations.
We strongly recommend that you take advantage of the expertise of Nemetschek’s technical support staff. We are happy to help you!



Solution:

The following description shows how to change several workstations where Allplan is installed locally and the project data is also stored locally on each computer to workstations with a common network drive without Workgroup Manager.

1st - getting ready
Choose one of the workstations where you will install all the projects and the office standard (hereinafter referred to as the main workstation).
First, move all the projects to the main workstation.

1.a: copying resources into projects
To make sure that the projects in your office have a uniform appearance, change the path settings for the projects' resources to 'Project'.
Make the following setting for each project:
Allplan -> File menu -> ProjectPilot - Admin -> select the individual projects one after the other -> right mouse button -> Properties -> Settings tab
Set the path settings for 'Pen and line definitions', 'Fonts', 'Patterns, hatching styles, area styles', 'Bar and mesh cross-section catalogs', 'Layer structures, line styles, drawing types' and 'Attributes proposed' from 'Office' to 'Project', if necessary.
The corresponding elements are copied from the office standard directly to the project. This ensures that the project settings stay the same even when you copy the project to the new server with the new office standard.

1.b: same folder name as project name
Open the 'General' tab and select the 'Same folder name as project name' setting if you want to proceed as described in 2b.

1.c: pen color ("Color stands for pen")
The pen color for the "Color stands for pen" setting is a user-specific setting that is not saved in the project but in the user folder (...\Usr).

2.a: backing up projects of the individual workstations and importing them to the main workstation (recommended method):
Back up the individual projects. To do this, open the Services application and select Data Backup -> Create -> Entire folders -> Projects.
You can back up several projects in a single operation.
Before you start, specify the backup folder on the network or on the local hard disk: Services application -> Configuration -> Backup path ->Browse for Folder.

The next step is to import the saved projects to the main workstation.To do this, open theServices application -> Data Backup -> Import -> Projects Before you import the individual projects, you can create new Allplan projects at the main computer. As an alternative, you can also create a new project during the import.

2.b: backing up projects of the individual workstations and importing them to the main workstation (special approach):
This approach should only be used with good reason for exceptional cases as it requires in-depth knowledge of Windows.
With this method, Windows Explorer is used to import the projects to the main workstation.
If some project names exist twice, you need to rename these projects before you back them up.

You can then rename the existing 'project.dat' file in the Prj folder of the main workstation.
Next, select the Services application -> Service -> Hotline Tools -> reorg -> Restore project management file.
The system creates a new project administration file (project.dat), which should list all projects with names.

Now the main workstation contains the latest version of all the projects of the office.

3rd - merging project defaults
Open ProjectPilot at the individual workstations and copy the elements you want to transfer (symbols, smart symbols, lists, schedules, and so on) to the external path. Of course, you can set the external path to a common network folder that can be accessed by all workstations.
Next, open ProjectPilot at the main workstation and copy the contents of the external path to the office standard.

4th - data backup

  • Back up the projects, office standard and user settings at the main workstation:
    You can also copy the ..\prj (projects), ..\std (office standard) and ..\usr (user folder) paths to a backup folder (Nemsic, for example) on the hard disk.
  • In addition, you need to back up the ..\usr\local folder at every stand-alone computer.
  • Export the user interface setting of each user to a file: Allplan -> Tools - > Customize .... -> Export...


5th - uninstalling
Remove Allplan from all workstations.

6th - reinstalling
Before you install the same version again, create and share a folder (Nemdata, for example) on the future data server. Create a subfolder - Allplan - in this folder.

The next step is to reinstall the same version on all the workstations.

Specify the following installation paths:
Program folder:
local (C:\Programs\Nemetschek\Allplan, for example)
Central file storage folder:
Browse -> Network...
Find the sharedNemdata folder and select the Allplan folder.

After this, start installing.

7th - testing the start and restoring the backup
After the installation (check whether Allplan starts), copy the ..\prj and ..\std folders you backed up from the main workstation to the new ...\Nemdata\Allplan server folder.

Next, use Windows Explorer to copy the contents of the former user folder (…\usr\local) of the stand-alone workstation to the new user folder of the computer you just installed.

8th - updating the project administration file
Go to the project.datfile in the ...\Nemdata\Allplan\Prjfolder and rename itproject.alt.After this, do the following:
Services application -> Service -> Hotline Tools -> reorg -> Restore project management file.

9th - summary
Now all the workstations access a common network drive with the same project pool and office standard.
With this type of installation, only one user can access a project at any one time. If several users are to work on a project at the same time, you need to install Workgroup Manager.

Download PDF  FAQ_EN_Switching_from_single_installation_to_network...
Version:  Allplan BCM 2014 / Allplan BCM 2013 / Allplan BCM 2012 / Allplan BCM 2011 / Allplan BCM 2009  | Last modified: 21.06.2021 10:18
Not voted yet. Be the first to vote this FAQ as helpful!

Question:

How can I export and import projects using Allplan Building Costs?



Note:


The following FAQ describes this topic only briefly.
For detailed information, please refer to the help by clicking Help -> Contents and Index:
Backing up data and archiving projects -> Backing up and archiving projects using archive administration -> Backing up projects


Note:

If you have received data from us or if you send data to us, please read the &apos;Important information&apos; section at the end of this FAQ!

Exporting:

  • SelectProject data -->Archive...; the Archive Administration dialog box opens.
  • Click Pathand set the archive folder.
  • Please make sure that Formatis set to Archive (version 4.0 and later).You can find this setting at bottom right.
  • Select the project you want to archive in the list box on the left.
  • ClickArchive projectto start backing up the data.
  • The project appears in the list box on the right.
  • As a result, the program has created an XXX.arafile.


Importing:

  • StartAllplan Building Costs.
  • SelectProject data -->Archive...
  • Click Pathand set the archive folder.
  • The project appears in the list box on the right; select it and click Restore archive.
  • If the program asks whether you want to create a copy, you are advised to do this to protect existing data.
  • The project appears in the list box on the left; you can now edit it.




Important information:

You can use this type of archiving to back up project data. Please note that this backup does not contain the complete database!
This type of archiving is very useful if you want to transfer data to technical support.
If you send a project, please do not forget to provide us with a detailed description of the problem.
This description should include the following information:

  • Program and version
  • When does the error occur? Or what did you do when the error occurred?
  • What does the error message say? A screenshot would be very helpful.
    (Pressing the Printkey copies the current contents of the screen to the Clipboard. Using CTRL+V, you can paste this screenshot into a Word document, save this file and send it to us.)
  • Office name or customer number and telephone number so that we can contact you.

We kindly ask you not to make any changes in the project in the meantime.

A note on fixed projects:
Please do not copy any data from a corrupt project to a fixed project as this may transfer the corrupt data to your current project!

Download PDF  FAQ_EN_Exporting_importing_projects_.pdf